Tallebudgera Creek set for dredging

Tallebudgera Creek set for dredging

The annual dredging of Tallebudgera Creek is about to begin.

The dredge is expected to be in place in the Creek on Monday 13th July, with a start date in a few days time.

It is expected the dredging itself will last approximately 8 weeks, concluding around 19th September, just before the September School Holidays.

Sand dredged from the campaign follows the pipeline around Burleigh headland to replenish Burleigh and other beaches to the north.

For any queries, please phone Councillor Daphne McDonald’s office on (07) 5581 6228

(Image from Neumann Contractors)